OP
Maverick777
I think the two extra cut outs are the supply to the garage and not correct for the job.
Follow along with the video below to see how to install our site as a web app on your home screen.
Note: This feature may not be available in some browsers.
Discuss Earth Loop Impedance Test and problem with power supply in the Periodic Inspection Reporting & Certification area at ElectriciansForums.net
another example maybe of "electrician" condemning a C/U without any valid reason maybe?...lol.....reminds me of this PIR we got for this rented a bit back from this "sparky"..lol.......sparky that gave gas and water bonding using a single continuous 10mm conductor as a (1)....lolffs....Apart from the reverse polarity has the electrician said why you need a board change?
surely the option here would be to replace the RCD....if the C/Us good for continued service...then just being "old school" is not acceptable reason to replace it is it?....as long as its in good order (IP)...and disconnection times are being met......This is what Western Power engineer said after a visit:-
Hi both,
When I visited again on Saturday morning the cause of the crossed polarity was obvious.When the RCD was installed the tails in the grey twin cable were connected red-black in the top of the consumer unit.This particular type of unit needs to be black-red.It is probable that we removed the external fuse to enable the RCD to be installed and on completion the fuse was replaced.However polarity checks showed reverse polarity.To correct this the tails were reversed on top of the external cutout and this cured the problem.At this stage there was no electrical danger and it stayed that way until the shower developed a fault last week and the crossed tails were spotted by Lloyd.
We have now reconnected the tails the correct way round.We also carried out trip testing on the RCD and found it faulty at required sensitivity,also it trips when the consumer unit DP switch is operated.This unit needs to be replaced.
The consumer unit is also old school and could be upgraded with a combined segregated unit but Beesleys will advise what options you have.
We will pay for the visits on Thursday and Saturday ,the remaining work is your responsibilty to settle directly with your Contractor.
regards
Hi,
It would be great if any of you were in the Blackwood area of Gwent. Why are some of you thinking that our house is supplied by two power companies as one meter in post 20 is of the gas and one the electric. Is this what you meant?
Thanks
another example maybe of "electrician" condemning a C/U without any valid reason maybe?...lol.....reminds me of this PIR we got for this rented a bit back from this "sparky"..lol.......sparky that gave gas and water bonding using a single continuous 10mm conductor as a (1)....lolffs....
As most of the main subject has been covered, I thought I'd throw this in to the mix.
I'd also be concerned about that cable running through the gas meter box, it hasn't been sealed and it looks like it is a cavity wall box. So if there was a leak, it could leak into the cavity and cause an explosive enviroment.
I would call the gas company or a good plumber to see what can be done.
I don't want to scare any one by the way, it's just an observation
Reply to Earth Loop Impedance Test and problem with power supply in the Periodic Inspection Reporting & Certification area at ElectriciansForums.net