Been to start first fix of a couple of existing farm buildings. The owner has had a brand new 3 phase supply with no earth provided.
The issue is the farm buildings have been partially dug into a limestone hillside, no soil of any depth within 10m of buildings.
I'm looking for ideas for earthing, hammering rods in is impossible
Thanks