My friend has a conundrum regarding earthing the metal parts of his garage. It's an extension to his home which is on a TT supply, It's of concrete block construction with a metal roof, attached to timbers but touching 3 RSJ's which supports the whole roof. None of which is bonded. There are tw/e cables crossing over the beams, so I suggested 10mm equipotential bonding from the beans to the MET. Question is, what needs to be done with the roofing sheets, as bonding could be problematic and cause the roof to corrode? Any ideas would be most welcome.
 
 
My friend has a conundrum regarding earthing the metal parts of his garage. It's an extension to his home which is on a TT supply, It's of concrete block construction with a metal roof, attached to timbers but touching 3 RSJ's which supports the whole roof. None of which is bonded. There are tw/e cables crossing over the beams, so I suggested 10mm equipotential bonding from the beans to the MET. Question is, what needs to be done with the roofing sheets, as bonding could be problematic and cause the roof to corrode? Any ideas would be most welcome.

But what potential are these beams introducing?
 
Welcome to the forum, thanks for joining and asking your question! Have you got any photos of the job? It may help our members to give the appropriate advice!

Thanks
 
Thanks, I did the resistance check to the beams and it was 24K ohms, so in theory isn't extraneous, but I didn't check the roof sheets as they were touching the beams anyway. I'm assuming the equipotential bonding still applies to the the beams regardless as they are structural steels and within touching distance, however, it would appear to introduce an unnecessary risk, so perhaps bonding isn't the answer. It's a shame there's not more clarity in the regs for differing construction methods, and it leaves installers in a damned if you do or damned if you dont scenario.
 
Last edited:
Thanks, I did the resistance check to the beams and it was 24K ohms, so in theory isn't extraneous, but I didn't check the roof sheets as they were touching the beams anyway. I'm assuming the equipotential bonding still applies to the the beams regardless as they are structural steels and within touching distance, however, it would appear to introduce an unnecessary risk, so perhaps bonding isn't the answer. It's a shame there's not more clarity in the regs for differing construction methods, and it leaves installers in a damned if you do or damned if you dont scenario.

But if they aren't extraneous then why connect them to to the electrical system?
 
It's a shame there's not more clarity in the regs for differing construction methods, and it leaves installers in a damned if you do or damned if you dont scenario.
it is quite clear in the regs if it’s not extraneous then it doesn’t need bonding.
 
Thanks, I did the resistance check to the beams and it was 24K ohms, so in theory isn't extraneous, but I didn't check the roof sheets as they were touching the beams anyway. I'm assuming the equipotential bonding still applies to the the beams regardless as they are structural steels and within touching distance, however, it would appear to introduce an unnecessary risk, so perhaps bonding isn't the answer. It's a shame there's not more clarity in the regs for differing construction methods, and it leaves installers in a damned if you do or damned if you dont scenario.
Not really its clear in black and white. Not knowing the regs isnt the regs books fault.
 

Reply to Earthing roof beams and roofing sheets on an attached garage. in the The Welcome Forum area at ElectriciansForums.net

Similar Threads

  • Question
Thanks, The whole building isn't steel-framed, just the roof supports it's reinforced concrete only to the base with the exception of the garage...
Replies
2
Views
898
  • Question
The pointy TV aerial strapped to the chimney will attract the lightning more than a metal roof covering with no particularly pointy bits.
Replies
19
Views
2K
davesparks
D
T
  • Question
The reason the main bond has a larger cross sectional area requirement for PME/TNCS installations is because you are effectively creating a...
Replies
15
Views
3K
Deleted member 9648
D
W
Ha ha, Well, it certainly wouldn't have been left, sitting on anything like a 200ohm Ra!! lol!!
Replies
25
Views
4K
Engineer54
E
Thank`s for all of the replies guys, been very informative.
Replies
35
Views
4K

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electrical Goods - Electrical Tools - Brand Names Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

YOUR Unread Posts

This website was designed, optimised and is hosted by untold.media Operating under the name Untold Media since 2001.
Back
Top
AdBlock Detected

We get it, advertisements are annoying!

Sure, ad-blocking software does a great job at blocking ads, but it also blocks useful features of our website. For the best site experience please disable your AdBlocker.

I've Disabled AdBlock    No Thanks