Hi All
So i have just got a job of doing a rewire on a small flat, which includes change of DB etc... Currently this is fed from a 3 phase DB in a commercial premises below. The feed cable is over 25m long (16mm T&E). the client has asked for a sub main tennant meter to be installed. At the moment the only downstream protection for the domestic DB is a 50amp single pole type b breaker..
I could do with clarification when i come to install the new tennant meter, if i should be fitting a double pole isolation switch after the meter. (thinking along the same lines as required protection for meter tails over 3 metres.. Ive had a rummage through the blue book of knowledge but can't seem to find the required answer..
thanks Chris
So i have just got a job of doing a rewire on a small flat, which includes change of DB etc... Currently this is fed from a 3 phase DB in a commercial premises below. The feed cable is over 25m long (16mm T&E). the client has asked for a sub main tennant meter to be installed. At the moment the only downstream protection for the domestic DB is a 50amp single pole type b breaker..
I could do with clarification when i come to install the new tennant meter, if i should be fitting a double pole isolation switch after the meter. (thinking along the same lines as required protection for meter tails over 3 metres.. Ive had a rummage through the blue book of knowledge but can't seem to find the required answer..
thanks Chris