I am sure I know the answer to this question but am being told black is white so bear with me.
If we fit TIC 5KWp of panels on a 3.68KWp max output inverter my understanding is that the 16amp per phase rule is not breached and DNO pre-approval is not required to connect to the grid.
I am being brow beaten and told by a colleague that the wording of the definition of DNC is such that it is effectively the TIC and that the maximum output of the inverter is not relevant because a larger inverter could be fitted at a later date - Therefore DNO approval is required. I think this is nonsense but starting to doubt myself due to the weight of opposition.
Help!
Andy
I am sure I know the answer to this question but am being told black is white so bear with me.
If we fit TIC 5KWp of panels on a 3.68KWp max output inverter my understanding is that the 16amp per phase rule is not breached and DNO pre-approval is not required to connect to the grid.
I am being brow beaten and told by a colleague that the wording of the definition of DNC is such that it is effectively the TIC and that the maximum output of the inverter is not relevant because a larger inverter could be fitted at a later date - Therefore DNO approval is required. I think this is nonsense but starting to doubt myself due to the weight of opposition.
Help!
Andy