tarkioboy
DIY
I'm upgrading our electrical system by putting in a service meter/disconnect and main panel. Currently there's no ground from the main to the meter.
The meter is grounded but not sure how deep the rod is, so will be putting in two new rods. The feeders run through metal conduit through the floor joists and has two 90 degree bends, so pulling a copper ground through would be near impossible. I want to run the copper ground a different route. Can I connect it to the first ground rod, then to the second, then to the meter/disconnect?
The meter is grounded but not sure how deep the rod is, so will be putting in two new rods. The feeders run through metal conduit through the floor joists and has two 90 degree bends, so pulling a copper ground through would be near impossible. I want to run the copper ground a different route. Can I connect it to the first ground rod, then to the second, then to the meter/disconnect?