testing on the 2391 insulation resistance test rig
for three phase
isolate cb supplying s/p board
Check meter, test DB is not live
disconnect neutral
test between lines neutral and earth
test between lines and neural A repeat of above?
test between lines
reconnect neutral
for single phase
isolate rcd main isolator
Check meter, test DB is not live
link line busbar to neutral busbar
test between line and earth
ensuring strappers are brought into test
disconnect link
isolate dimmer circuit
test between line and neural
for three phase
isolate cb supplying s/p board
Check meter, test DB is not live
disconnect neutral
test between lines neutral and earth
test between lines and neural A repeat of above?
test between lines
reconnect neutral
for single phase
isolate rcd main isolator
Check meter, test DB is not live
link line busbar to neutral busbar
test between line and earth
ensuring strappers are brought into test
disconnect link
isolate dimmer circuit
test between line and neural