Did a PIR other day, and the lighting has been wired as a ring and not 2 radials.
Now, i could hunt around and try and split it, but i was wondering what your thoughts were on this.
Its been like it for a fair few years on a 6A MCB and the owner has never had a problem with overload.
In other words... mark it on report as satisfactory and note it on the deviations or not?