A
awarner
Morning all
I've got a lot of work coming up doing main gas bonding but its mostly going to be in commercial and industrial situations. I'll give you the following scenario.
Main DB is in building number 1, gas main comes into building number 2 on the same site. Blg 2 is fed , electrically, via a submain from bldg 1 and has its own DB.
BS7671 says that main bonding has to be taken to the MET, but in a situation such as this, is the main earthing terminal at Building 2 alright to go to or have I got to go to the lengths of getting the cable back to the MET in building 1?
Also, if the bond can be made in building 2, should the size of the bond (as per section 544 of the regs) be worked out on the mains coming into DB1 or the size of the submain going to DB2?
I'm scratching my head on this one at the moment and thanks for any advice you can give me.
I've got a lot of work coming up doing main gas bonding but its mostly going to be in commercial and industrial situations. I'll give you the following scenario.
Main DB is in building number 1, gas main comes into building number 2 on the same site. Blg 2 is fed , electrically, via a submain from bldg 1 and has its own DB.
BS7671 says that main bonding has to be taken to the MET, but in a situation such as this, is the main earthing terminal at Building 2 alright to go to or have I got to go to the lengths of getting the cable back to the MET in building 1?
Also, if the bond can be made in building 2, should the size of the bond (as per section 544 of the regs) be worked out on the mains coming into DB1 or the size of the submain going to DB2?
I'm scratching my head on this one at the moment and thanks for any advice you can give me.