Hi, but as spin was saying I cannot remove RCD protection where it is already provided because it makes the installation less safe. So, the question is whether this solution is ok?
Point of supply --- Meter --- Main isolator with RCD-S --- 30m of T&E (some surface, some hidden) --- Consumer unit with RCD
If the time delay RCD is not acceptable, then is my only option to provide additional mechanical protection on the 30m of cable, and if yes, is the additional mechanical protection required on the surface mounted cable as well as the hidden cable?