S

speedtronic

For phase to phase Meggering of 3-phase Synchonous Generator, we have to open its flexible links (between phases) & its star point. We then connect Megger's positive lead to phase (which we want to Megger) & we short remaining two phases with ground?(& connect megger's negative lead to it) Why?? What if we donot short other two phases with ground?
 
For phase to phase Meggering of 3-phase Synchonous Generator, we have to open its flexible links (between phases) & its star point. We then connect Megger's positive lead to phase (which we want to Megger) & we short remaining two phases with ground?(& connect megger's negative lead to it) Why?? What if we donot short other two phases with ground?

erm...nothing. All you are doing is IR checking between output windings. This is the same as, say, connecting together live conductors on an installation and IR checking between them to earth. If there is a fault there it will show up if you do them connected or IR test individually:)
 
please tell me that for phase to ground meggering of a 3-phase power T/F. Do we need to perform same practice? I mean like shorting of other two phases to ground?
Moreover, kindly tell me something about high pot. test. I know that it is used to measure maximum voltage withstanding capability of an equipment. BY injecting high voltage, what do we measure at output? & what should be its range?
Also kindly tell me about stator winding inter-turn faults? what they actually are? As I know, In case of inter-turn winding fault the current on both side of the winding is same so differential protection can not be used? then what kind of protection is used for it?
 

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Green 2 Go Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses Heating 2 Go
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

Advert

Daily, weekly or monthly email

Thread Information

Title
Meggering of 3-phase Synchonous Generator
Prefix
N/A
Forum
Talk Electrician Forum
Start date
Last reply date
Replies
2

Advert

Thread statistics

Created
speedtronic,
Last reply from
speedtronic,
Replies
2
Views
4,871

Advert

Back
Top