itchy
How do you test these things?
I'm trying to get readings for one home, but the site has one main box feeding about 80 homes. They've been installed on what I can only assume to be a giant final ring circuit. Where each one spurs off with a fuse board with an rcd. This then has about 20 meters of cable leading to the fuse board for the lighting circuit, ring main boiler etc in the home home. Which in turn has a fuse board next to it for the shower radial and kitchen ring.
How do you do live tests when one rcd trips down from the one you are testing. And secondly, ze?
Thanks, help me as my brain cannot cope today... I know i'm missing the obvious.
I'm trying to get readings for one home, but the site has one main box feeding about 80 homes. They've been installed on what I can only assume to be a giant final ring circuit. Where each one spurs off with a fuse board with an rcd. This then has about 20 meters of cable leading to the fuse board for the lighting circuit, ring main boiler etc in the home home. Which in turn has a fuse board next to it for the shower radial and kitchen ring.
How do you do live tests when one rcd trips down from the one you are testing. And secondly, ze?
Thanks, help me as my brain cannot cope today... I know i'm missing the obvious.