Hi all , We are carrying out a refit on a retail unit and the client wants us to provide a clean dB for the till power and the data cab. Can anyone clarify best practise for configuring this in the install .
The site currently has a 3 phase incomer with 60a fuses at the distributors side.
We are intending to install a schneider acti 9 TPN 8 way board with a 125A 4pole switch isolator to feed the general lighting and power. .
The intention was to go Into Henley blocks from the meter and then split to the TPN and off to a single phase board for the clean power . Is this correct ?
Many concerns are
1. If I install like this will the phases not be unbalanced ?
2 am I better off supplying the clean dB from a MCB in the TPN board?
3 can anyone give me general advice on best practice for balancing 3 phase DBS.
i know this is a large topic .
Any advice and help would be grateful . Many thanks in Advance
The site currently has a 3 phase incomer with 60a fuses at the distributors side.
We are intending to install a schneider acti 9 TPN 8 way board with a 125A 4pole switch isolator to feed the general lighting and power. .
The intention was to go Into Henley blocks from the meter and then split to the TPN and off to a single phase board for the clean power . Is this correct ?
Many concerns are
1. If I install like this will the phases not be unbalanced ?
2 am I better off supplying the clean dB from a MCB in the TPN board?
3 can anyone give me general advice on best practice for balancing 3 phase DBS.
i know this is a large topic .
Any advice and help would be grateful . Many thanks in Advance