Scrag
-
Just about to be enrolled on register (MCS). Cost so far £6000 plus (one man band) and not a penny turned over. I have been given an opportunity to do some subbing and they have supplies except for inverters. Believe they use SMA's and nothing else !!!!!!. Being in at the beginning of the end and desperate to get something back, what is the position of installing everything else and leaving the inverter till maybe after the 12th Dec. Hypothetically, What if one inverter was used for all installs for testing and registering etc and then when supplies come in fit them as required. Any input would be appreciated.