I have been doing some work for a hedgehog charity so funds have been tight.
I have remedied a number of non conformity items as they want an EICR for the landlord.
I am happy with the general condition of the circuits and readings are all within range. A number of C3s have been given, with one being lack of cable support in ceiling areas.
The shop has two Wylex boards one metalclad and one plastic. Neither has a lid for where the original rewirable fuses were as these have been replaced with MCBs of various types. I intend to replace the fuse carriers that have open pin connections to closed ones. Doing this, will it be sufficient to pass as there will still be no lid/cover on either board.
The boards are in a cupboard that is secure and only authorised staff have access to.
I have considered sourcing new lids but they would still need the cover cutting out so the MCBs would fit.
The final option is replacement DBs but I want to avoid the cost if I can.
Thanks for any replies.
I have remedied a number of non conformity items as they want an EICR for the landlord.
I am happy with the general condition of the circuits and readings are all within range. A number of C3s have been given, with one being lack of cable support in ceiling areas.
The shop has two Wylex boards one metalclad and one plastic. Neither has a lid for where the original rewirable fuses were as these have been replaced with MCBs of various types. I intend to replace the fuse carriers that have open pin connections to closed ones. Doing this, will it be sufficient to pass as there will still be no lid/cover on either board.
The boards are in a cupboard that is secure and only authorised staff have access to.
I have considered sourcing new lids but they would still need the cover cutting out so the MCBs would fit.
The final option is replacement DBs but I want to avoid the cost if I can.
Thanks for any replies.