Hi all, I have just carried out a 50% EICR on a property as the builders usual electrician (loosely used term here ) has said that the job is too much for him to tackle after usual work hours for his proper boss on the private for this builder !
He cannot test and hasn't got kit or knowledge anyway, no insurance and so on.. so now after finding a lot of issues on the report he has asked me to estimate it. The problem being I already know it needs broken consumer unit replaced but also many coded problems worked through and sorted first, then new board and full certs for all of it.
From what I saw on 50% look and test it will be at least a 40hr week or more to look into the issues and start to rectify without thinking of touching the board.
Estimating something like this I am thinking of the rough hours halving ring finals etc.. breaking down legs for IR tests and so on then at least the new board and other materials on top plus time allowed for certs and a little dollop on top too for any unforseen plus hassle contingency !
Ping the figure out and see if he goes for it.
What do you think about this kind of thing ? My old boss used to apply a 1.7 or 2 x multiplier onto all his works and air con too after pricing all materials and that seems really rough but also far less time consuming but got 90% of his jobs like that and made a packet.
Thanks.
He cannot test and hasn't got kit or knowledge anyway, no insurance and so on.. so now after finding a lot of issues on the report he has asked me to estimate it. The problem being I already know it needs broken consumer unit replaced but also many coded problems worked through and sorted first, then new board and full certs for all of it.
From what I saw on 50% look and test it will be at least a 40hr week or more to look into the issues and start to rectify without thinking of touching the board.
Estimating something like this I am thinking of the rough hours halving ring finals etc.. breaking down legs for IR tests and so on then at least the new board and other materials on top plus time allowed for certs and a little dollop on top too for any unforseen plus hassle contingency !
Ping the figure out and see if he goes for it.
What do you think about this kind of thing ? My old boss used to apply a 1.7 or 2 x multiplier onto all his works and air con too after pricing all materials and that seems really rough but also far less time consuming but got 90% of his jobs like that and made a packet.
Thanks.