Hi guys and Gals
just a quickie this is to clarify a point
Recently carried out PIRs to 9 small commercial units on an commercial park. you know the sort of thing.
5 of these were unsatisfactory and required remedial works.
these works have now been carried out by either myself or the tenants.
Obviously pager 2 is now clear or faults
Question is.. do i issue a completely new Certificate including continuation sheets or can i get away with just issuing a page 2.
What is the criteria on this? .
any feedback would be appreciated
sparky692
just a quickie this is to clarify a point
Recently carried out PIRs to 9 small commercial units on an commercial park. you know the sort of thing.
5 of these were unsatisfactory and required remedial works.
these works have now been carried out by either myself or the tenants.
Obviously pager 2 is now clear or faults
Question is.. do i issue a completely new Certificate including continuation sheets or can i get away with just issuing a page 2.
What is the criteria on this? .
any feedback would be appreciated