After the episode I mentioned above there was a major rethink.

The data centre was split between two sites. Each was fed via two auto change over LV supplies with UPS. The two LV feeds were from different sides of the main MV boards. We had two intake substations each with a pair of 20MVA 33/11KV transformers.

For the two centres to fail entirely, all four intake transformers would have to fail. About the only way that could happen would be the 132KV grid failing totally.
 

Reply to the thread, titled "Phases In A Server Room" which is posted in Commercial Electrical Advice on Electricians Forums.

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electrical Goods - Electrical Tools - Brand Names Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

Daily, weekly or monthly email

Back
Top