Looking at a job to price for some remedial work. 2 things i have noticed and mentioned it to the customer are, no RCD on shower circuit nor on the upstairs lighting circuits. This has been listed as code 4, not to current regs.
I have said it should be a code 2 and need doing asap.
This report has been done, no code 1's but code 2's, so should be classed as unsatisfactory, right?
I have said it should be a code 2 and need doing asap.
This report has been done, no code 1's but code 2's, so should be classed as unsatisfactory, right?