Hi there I have been asked to put a quote in for the labour on running Armoured SWA cable to 6 flats and landlords supply (7 all in all).
There will be about 160 meters of 25mm SWA needed (Roughly).
Ryefield three phase board installed.
Glanded and connected to 6 consumer units, walls will need to be chased out along a hallway with doors made for access to the cable (chasing, clipping, screwing my job, boxing and doors will be chippies)
There is also a landlords consumer unit to provide and 100amp isolation switches after the meters to be installed as well.
and a 4 inch hole needs to be made for the EDF supply (about 1 meters worth)
I was thinking it would take about 5 days to complete, and would be happy with ÂŁ400 a day?
They are supplying materials.
Would that be a fair price or am I ripping of the customer - or myself ?
Cheers
GREG
There will be about 160 meters of 25mm SWA needed (Roughly).
Ryefield three phase board installed.
Glanded and connected to 6 consumer units, walls will need to be chased out along a hallway with doors made for access to the cable (chasing, clipping, screwing my job, boxing and doors will be chippies)
There is also a landlords consumer unit to provide and 100amp isolation switches after the meters to be installed as well.
and a 4 inch hole needs to be made for the EDF supply (about 1 meters worth)
I was thinking it would take about 5 days to complete, and would be happy with ÂŁ400 a day?
They are supplying materials.
Would that be a fair price or am I ripping of the customer - or myself ?
Cheers