Hi chaps,
Just did a "mock" EICR on a friends place and found no bonding to incoming gas and water.
Am I allowed to use a single piece of 10mm to bond both of them back to the MET, or does it have to be 2 separate runs? Fairly sure 1 run is ok, but just wanted to be sure!
Sorry for the amateurish question!
Just did a "mock" EICR on a friends place and found no bonding to incoming gas and water.
Am I allowed to use a single piece of 10mm to bond both of them back to the MET, or does it have to be 2 separate runs? Fairly sure 1 run is ok, but just wanted to be sure!
Sorry for the amateurish question!