A032701
-
A customer has asked for a complete rewire for their house that they are doing work on. he has had to put in a new floor everywhere downstairs as it was wooden joists and he wants it solid. He is building it up with hardcore then a concrete subfloor on top of that (about 4 inches). on top of that there is dpm then celotex, he is having UFH so that will go on top of the celotex followed by screed.
what would be the easiest way to run the ring for the sockets. i want to try and avoid running it in the ceiling void and dropping down to the sockets as it will mean taking up a lot of floorboards.
thanks
what would be the easiest way to run the ring for the sockets. i want to try and avoid running it in the ceiling void and dropping down to the sockets as it will mean taking up a lot of floorboards.
thanks