I am setting up some temps on a small site consisting of approx 3 110 transformers 2 portacabins offices sitting on top of each other, a portacabin toilet and a portacabin drying room.
The supply is a 3 phase DB.
Im thinking use 1 phase for the trannys, 1 phase for the offices and the other phase for the loos/drying room.
My colleague says we should use just 1 phase for the toilets/drying room/offices because of the potential 400v across the phases however that would leave one phase unused and a very unbalanced load.
Any advice welcome.
cheers