N
ngoodson1969
Hi,
I was asked to quote for a rewire on a 1 bed flat. I included a heat and a smoke in the quote but was told by the company that are developing it to remove these as they have a contract with Brighton Fire Alarms. Should this be written in the EIC as a limitation/notice or something or should I insist that for the small price of a smoke and a heat alarm anyway that I couldn't rewire without them.
Cheers
Nick
I was asked to quote for a rewire on a 1 bed flat. I included a heat and a smoke in the quote but was told by the company that are developing it to remove these as they have a contract with Brighton Fire Alarms. Should this be written in the EIC as a limitation/notice or something or should I insist that for the small price of a smoke and a heat alarm anyway that I couldn't rewire without them.
Cheers
Nick