Hi All
I have read the previous thread on this but just wanted some help with a project we are about to complete.
we are set up already for 3 phase we have a panel board 3 phase with metering to 6 outgoing circuits, we have 5 3 phase boards in the mains room, 2 3 phase panels fed from 2 distribution boards, 1 3 phase going to another building fed from the panel board.
all circuits are now terminated & ready for testing & inspection & have been for some time, we have had the TBS supply jointed & power over to the new building ready to go, 3 phase head installed on the TBS & on the new building but turns out we only have split phase, this did not matter on the TBS as we only needed single phase.
so it has come to light now, our paperwork completed & information fro UKPN was that we were having 3 phase but now only found out they only have split phase at & around the site, I am not involved in the paperwork side but I can guess what is happening that we are being asked to probably pay for the upgrade.
we only have a few things that are going to be 3 phase so could use convertors that's not what I am looking at it is the distribution system we have built for 400v 3 phase & ripping it out & converting to split phase.
anyone recommend or used split phase equipment as in PB & DB's if so where did you get the equipment or is there a way we could convert what we have ? any help would be appreciated
I have read the previous thread on this but just wanted some help with a project we are about to complete.
we are set up already for 3 phase we have a panel board 3 phase with metering to 6 outgoing circuits, we have 5 3 phase boards in the mains room, 2 3 phase panels fed from 2 distribution boards, 1 3 phase going to another building fed from the panel board.
all circuits are now terminated & ready for testing & inspection & have been for some time, we have had the TBS supply jointed & power over to the new building ready to go, 3 phase head installed on the TBS & on the new building but turns out we only have split phase, this did not matter on the TBS as we only needed single phase.
so it has come to light now, our paperwork completed & information fro UKPN was that we were having 3 phase but now only found out they only have split phase at & around the site, I am not involved in the paperwork side but I can guess what is happening that we are being asked to probably pay for the upgrade.
we only have a few things that are going to be 3 phase so could use convertors that's not what I am looking at it is the distribution system we have built for 400v 3 phase & ripping it out & converting to split phase.
anyone recommend or used split phase equipment as in PB & DB's if so where did you get the equipment or is there a way we could convert what we have ? any help would be appreciated