I'm after some opinions please.
Full rewire, original agreement was payment on completion of first fix, then second fix then on completion.
Project has had "a few" unscheduled" pauses (caused by other trades) so payments were agreed to be at month ends. All was going well until submission of my March invoice which hasn't been paid, and still hasn't.
Client is now saying they won't pay until its all done, completed and tested.
Whilst I could accommodate this change its leaving me awfully short of cash and my concern now is what if they delay payments again I'll be in trouble with the bank.
My inclination is to complete the live testing then remove the busbars from the CU until they pay .....
How would approach this?
Full rewire, original agreement was payment on completion of first fix, then second fix then on completion.
Project has had "a few" unscheduled" pauses (caused by other trades) so payments were agreed to be at month ends. All was going well until submission of my March invoice which hasn't been paid, and still hasn't.
Client is now saying they won't pay until its all done, completed and tested.
Whilst I could accommodate this change its leaving me awfully short of cash and my concern now is what if they delay payments again I'll be in trouble with the bank.
My inclination is to complete the live testing then remove the busbars from the CU until they pay .....
How would approach this?