Hi
I have reviewed a few posts around this subject, but my question is not covered. I know that the Submain Earth has to be sized on the DNO incomer, not on the submain to the external building itself. My question is if I need two main bonds in the submain building, for example one for ground fed metal pipe for water and ground fed metal pipe work for gas, does that mean the equivalent earth sizing of the armoured / extra conductor in the armour, must also be sized to take account of 2 x 10mm or just one 10mm (example assumes TNCS with 25mm Line. Or is there something in the regs that assumes one fault to earth only and not multiple?
Thank you.
John
I have reviewed a few posts around this subject, but my question is not covered. I know that the Submain Earth has to be sized on the DNO incomer, not on the submain to the external building itself. My question is if I need two main bonds in the submain building, for example one for ground fed metal pipe for water and ground fed metal pipe work for gas, does that mean the equivalent earth sizing of the armoured / extra conductor in the armour, must also be sized to take account of 2 x 10mm or just one 10mm (example assumes TNCS with 25mm Line. Or is there something in the regs that assumes one fault to earth only and not multiple?
Thank you.
John