Hi,
Sorry if this has been covered already......
We have been 'subbed' in to carry out the electrical work/commissioning for a company just about to do their MCS assessment.
They will do the roof work,mounting etc and we will do all inside works,AC and DC.
What paperwork is our responsibility as an installer?
I assume that we should fill out a PV checklist and a PV Array test form and also an Electrical Installation Certificate,as we would usually do.
What about the Commissioning form?
Our own headed commissioning form has all our details inc. our accreditation/qualification reference,so should we just delete these details and leave this blank for the main contractor to fill out or is all commissioning information the responsibility of the main contractor?
Thanks.
P.S.We currently do the same for Wind turbines for another company and all we have to provide them with is an Electrical Installation certificate!
Sorry if this has been covered already......
We have been 'subbed' in to carry out the electrical work/commissioning for a company just about to do their MCS assessment.
They will do the roof work,mounting etc and we will do all inside works,AC and DC.
What paperwork is our responsibility as an installer?
I assume that we should fill out a PV checklist and a PV Array test form and also an Electrical Installation Certificate,as we would usually do.
What about the Commissioning form?
Our own headed commissioning form has all our details inc. our accreditation/qualification reference,so should we just delete these details and leave this blank for the main contractor to fill out or is all commissioning information the responsibility of the main contractor?
Thanks.
P.S.We currently do the same for Wind turbines for another company and all we have to provide them with is an Electrical Installation certificate!