been asked to install a supply to a hot tub.
old one that is there has been fitted to a board in a shed.
the feed to the shed db is 2.5mm then at the house 6mm.
there is no power there due to tripping.
i want to install a new supply and get rid of all that.
they may be getting rid of the shed and asked for the new board closer to the tub area.
so a ip65 cabinet will be fitted.
my confusing is that the house db has a spare rcd way.
i was thinking of running a swa to a sub board with just a main switch and mcbs and relying on the house rcd to proctect.
reason for the board is they what the sockets and shed to still work.
the earthing is a TN-S setup.
in my head i cant see why its a problem as its still being protected by a rcd.
old one that is there has been fitted to a board in a shed.
the feed to the shed db is 2.5mm then at the house 6mm.
there is no power there due to tripping.
i want to install a new supply and get rid of all that.
they may be getting rid of the shed and asked for the new board closer to the tub area.
so a ip65 cabinet will be fitted.
my confusing is that the house db has a spare rcd way.
i was thinking of running a swa to a sub board with just a main switch and mcbs and relying on the house rcd to proctect.
reason for the board is they what the sockets and shed to still work.
the earthing is a TN-S setup.
in my head i cant see why its a problem as its still being protected by a rcd.