1Justin

-
Arms
Joined
May 20, 2011
Messages
497
Reaction score
169
Location
Surrey
My customer needs bigger than 60A supply. Currently BS1361 60A. 4 bedroom house, 4 kids, new circuits..

Before I started in the place it came up at 72A (with diversity), and after my 2 new circuits I am 79A (with diversity). PME, nice condition, modern supply cable, Ze 0.27 so should be able to take 80A fuse).

Given the additions, however I look at it and use diversity I need 80A.

Since I'll be inspected on this job (Mr NICEIC etc), I am sure this needs to be shown to be all ticked off OK. The quote from SSE is ÂŁ131.42+VAT to upgrade the fuse. Surely all they are likely to do is confirm Ze, check the supply cable and earthing conductor, and change the fuse. (modern cable and 16mm main earthing conductor).

Is this a typical quote? I haven't told the customer yet but he's not going to like it given that in his eyes he gets nothing for it.

Is someone here now going to tell me that they just change the fuse anyway without informing DNO? DNO never seem know what the fuse rating is anyhow when I've asked them before.

Justin
 
Whack lots of high current loads on the system and I bet a pound to a penny,you will be surprised at what it doesn't pull
Add to that,the 60 amp fuse will take quite a bit more than that for quite some time and ÂŁ100+ pounds may be unnecessary cost

As long as your system can cope with a 80 or 100 amp supply,the supply itself is a seperate issue. unless that 60 amp gets roasted
of course
 
I'm just trying to work out why they would charge 130+ quid to up-grade a fuse?? Isn't that what your paying a monthly standing charge for?? A few years ago the local DNO was going round upgrading 60A service fuses for 80A fuses, while changing/upgrading the meters (40 max)... No charge was ever levied.
 
My customer needs bigger than 60A supply. Currently BS1361 60A. 4 bedroom house, 4 kids, new circuits..

You sure about that?! I've just built a massive four bed, ground source, water bore, treatment, sewerage, the works..... currently sitting on an 80A. The DNO knows about it, the customer knows about it. If it goes pop in the winter then there's a ÂŁ4k bill to change the pole transformer, so we'll all just wait and see. Diversity came out at something like 220A.
 
as des and tony's posts. leave well alone. just reduce the max. demand figure on your cert.

when i moved into my dad's house ( 1988 ), it ran at a calculated 85A total load for 2 years on a 30A rewireable, before it finally died.
 
Last edited:
You sure about that?! I've just built a massive four bed, ground source, water bore, treatment, sewerage, the works..... currently sitting on an 80A. The DNO knows about it, the customer knows about it. If it goes pop in the winter then there's a ÂŁ4k bill to change the pole transformer, so we'll all just wait and see. Diversity came out at something like 220A.

What are you getting when you clamp the tails? Im just interested in whats being pulled, from almost a worst case scenario, going by what youve posted
 
The charge is obviously just a standard service fee as it's you that are calling them.

I'd wait and if it blows the chances are whoever comes from SSE will most likely fit an 80a replacement.

Tell the client the costs and let them make the decision, and tell them to keep a big pack of Hobnobs on standby just in case SSE have to come, might even get a 100a for that.
 
Last edited:

Reply to Supply fuse - quote to change. in the UK Electrical Forum area at ElectriciansForums.net

News and Offers from Sponsors

  • Article
Join us at electronica 2024 in Munich! Since 1964, electronica has been the premier event for technology enthusiasts and industry professionals...
    • Like
Replies
0
Views
265
  • Sticky
  • Article
Good to know thanks, one can never have enough places to source parts from!
Replies
4
Views
756
  • Article
OFFICIAL SPONSORS These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then...
Replies
0
Views
745

Similar threads

  • Question
There's a church in a town near me that has solved the heating problem for most days by building what is essentially a large timber and glass...
2
Replies
27
Views
2K
If the shared neutral is lost ,won`t you be getting 400v across both cottages? 2 phase US style but double the Voltage.
Replies
22
Views
3K

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electrical Goods - Electrical Tools - Brand Names Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

YOUR Unread Posts

This website was designed, optimised and is hosted by untold.media Operating under the name Untold Media since 2001.
Back
Top