Hi,
Im hearing contridicting info on this.
When i was in college my tutor told me if SWA was used in a way as it was 3 core and one the cable was the earth then the SWA only needs earth glanding and fly cable on one side of the terminated SWA. But ive seen a couple PIRs pick this up as a fault as needing amended to earthed with fly cable both sides.
which is correct?
Obv it cant never hurt to do both sides, but does one side in this case meet regulations?
Im hearing contridicting info on this.
When i was in college my tutor told me if SWA was used in a way as it was 3 core and one the cable was the earth then the SWA only needs earth glanding and fly cable on one side of the terminated SWA. But ive seen a couple PIRs pick this up as a fault as needing amended to earthed with fly cable both sides.
which is correct?
Obv it cant never hurt to do both sides, but does one side in this case meet regulations?