You might remember this delight from the dodgy trade pictures thread....
I finally got back to quote for sorting today.
The chicken and egg question was whether the plumber or the sparks did this. The confusion was there were no fixing holes visible from a previous position. Yet the water pipe is in line with the incoming supply arriving in MPDE though a screed floor. But the insulation is stripped back suggesting it was once in a sensible place.
It was when I noticed that next door's identical house didn't have the door that I was using that the penny dropped.
Yep, new door; the builder did it!
Ok, let's look inside....
So apart from mis-matched devices, being held by one dry-wall screw to the ceiling, wiring stretched to the limit, and IP rating being seriously compromised, it's fine!
Then I saw it:
House is and always has been PME. I'm very familiar with this estate and they are all Legrand normal split load boards. Why the ---- is it a100ma device?!?! Surely that's got to be someone messing up when replacing a failed RCD?
Anyway, a new RCBO board would solve a lot of issues, as hopefully the Neutral's will then reach. And they are only using 12 ways so a smaller board should fit. I have a feeling there's some fun ahead here.
I finally got back to quote for sorting today.
The chicken and egg question was whether the plumber or the sparks did this. The confusion was there were no fixing holes visible from a previous position. Yet the water pipe is in line with the incoming supply arriving in MPDE though a screed floor. But the insulation is stripped back suggesting it was once in a sensible place.
It was when I noticed that next door's identical house didn't have the door that I was using that the penny dropped.
Yep, new door; the builder did it!
Ok, let's look inside....
So apart from mis-matched devices, being held by one dry-wall screw to the ceiling, wiring stretched to the limit, and IP rating being seriously compromised, it's fine!
Then I saw it:
House is and always has been PME. I'm very familiar with this estate and they are all Legrand normal split load boards. Why the ---- is it a100ma device?!?! Surely that's got to be someone messing up when replacing a failed RCD?
Anyway, a new RCBO board would solve a lot of issues, as hopefully the Neutral's will then reach. And they are only using 12 ways so a smaller board should fit. I have a feeling there's some fun ahead here.