I have my NIC inspection on the 9th of March. Most of my work has been out of my area but I've had
a small site since November 15mins away which I had planned to take assessor to. Problem is the site has run quite a bit over due to roofing issues etc.
I will have two of the plots 2nd fixed this week, ready for testing beginning of next week, only thing is none of the showers will have been fitted or outside lights (client not decided).
Would you take assessor here or would I get pulled for testing etc without everything being fitted?
I'm really trying to pass this first time so I'd hate to get pulled for something stupid like this.
Thanks in advance
a small site since November 15mins away which I had planned to take assessor to. Problem is the site has run quite a bit over due to roofing issues etc.
I will have two of the plots 2nd fixed this week, ready for testing beginning of next week, only thing is none of the showers will have been fitted or outside lights (client not decided).
Would you take assessor here or would I get pulled for testing etc without everything being fitted?
I'm really trying to pass this first time so I'd hate to get pulled for something stupid like this.
Thanks in advance