F
Fred Faulkner
Hi guys,
i had a look at a building in the west end of london which is spilt into 10 flats this weekend to do some upgrading works to the landlord area.
i noticed that there was originally 6 flats and the landlord must of added an addition 4 flats on top. Called 10 9 8 7. ( obviously).
The issue is that there has been a 3 phase submain wired in swa from the ground floor ryefield board . Which is then terminated into a 3 phase board installed outside flat 10/9 . From this board they have wired the two flats using all three phases therefore giving a potential of 400v across the circuits installed into the flats!!
i.e
flat 10 1L1 - lighting
flat 10 1l2 - smoke alarms
flat 10 1l3 - sockets
flat 10 2L1 - cooker
flat 9 is the same i.e
3L1 lighting
3l2 smokes etc etc!
this senario is the same for flat 8 7 !
im sure this is hugely wrong!!!
i had a look at a building in the west end of london which is spilt into 10 flats this weekend to do some upgrading works to the landlord area.
i noticed that there was originally 6 flats and the landlord must of added an addition 4 flats on top. Called 10 9 8 7. ( obviously).
The issue is that there has been a 3 phase submain wired in swa from the ground floor ryefield board . Which is then terminated into a 3 phase board installed outside flat 10/9 . From this board they have wired the two flats using all three phases therefore giving a potential of 400v across the circuits installed into the flats!!
i.e
flat 10 1L1 - lighting
flat 10 1l2 - smoke alarms
flat 10 1l3 - sockets
flat 10 2L1 - cooker
flat 9 is the same i.e
3L1 lighting
3l2 smokes etc etc!
this senario is the same for flat 8 7 !
im sure this is hugely wrong!!!