L
LlandrilloSpark
fellas can anybody give a rough idea of a price on this before I go in for it!
18 circuits moving from a 3 phase board to another 3 phase board 20m away, its a large commercial shop open from 7am-10pm every day, install uses basket above the false poly tile ceiling.
SP are putting the new supply in so i know i need to buy an 18-24way board and hang it ready then do the fabrication in the ceiling then move the circuits one by one along with the MCB's.
power has to be on as much as possible, circuits off for minutes only, loads of H&S issues as ill be working around customers.
I thought ÂŁ1800-ÂŁ2300?, i have to give him a minimum price and max as i doubt i can get the nail on the head.
cheers
18 circuits moving from a 3 phase board to another 3 phase board 20m away, its a large commercial shop open from 7am-10pm every day, install uses basket above the false poly tile ceiling.
SP are putting the new supply in so i know i need to buy an 18-24way board and hang it ready then do the fabrication in the ceiling then move the circuits one by one along with the MCB's.
power has to be on as much as possible, circuits off for minutes only, loads of H&S issues as ill be working around customers.
I thought ÂŁ1800-ÂŁ2300?, i have to give him a minimum price and max as i doubt i can get the nail on the head.
cheers