olsonn
Does anybody out there recognise this type of installation. I have never come across anything like it before. I was doing some work on a flat yesterday that had a few problems. The incoming water pipe was not bonded and the earthing cable on the gas pipe was not attached. The installer had also obviously had some problems with cable lengths and had put the tails from the socket ring circuit on 2.5mm into a JB and had then taken a single 6mm cable into the CU. Has anybody else seen this method used before and does it meet the regs. I was going to replace this with 2 seperate 2.5mm tails