evening-hope we are all enjoying the white stuff!!
I looked at a promising job last night- its a old retail style place which is being devoloped into 1x mews house and 3x 1bed apartments.
In the tender pack- it states they will be getting a new 3phase supply put into a communal cycyle store then from here- it would be for me to distribute to the mews house and apartments+ 1x small LL board for 5x communal lights and a elec gate.
But they want the supply meters inside the apartments/mews house as apposed to in the communal cycle store.
can i take the new 3phase supply into a Ryefeild- then into switched isolators- swa sub main into the properties- then have the meter in there then into the consumer units
but then the SWA sub-main will be un-metered..
I looked at a promising job last night- its a old retail style place which is being devoloped into 1x mews house and 3x 1bed apartments.
In the tender pack- it states they will be getting a new 3phase supply put into a communal cycyle store then from here- it would be for me to distribute to the mews house and apartments+ 1x small LL board for 5x communal lights and a elec gate.
But they want the supply meters inside the apartments/mews house as apposed to in the communal cycle store.
can i take the new 3phase supply into a Ryefeild- then into switched isolators- swa sub main into the properties- then have the meter in there then into the consumer units
but then the SWA sub-main will be un-metered..