T
TedM
Over on the Navitron Forum one user with a PV system that has recently been extended has highlighted a problem.
He had a system installed before EPCs came in and has had an extension installed and commissioned in July this year - just before the 1st August deadline.
He previously did not have an EPC but obviously needed one for the extension.
He had his system installed and commissioned on 26th July and the EPC done on 27th July.
EDF, his FiT supplier, have said that he must go on the 9p rate for the extension as he did not have an EPC 'D' on the required date. They have cited OFGEM guidance on this from here http://www.ofgem.gov.uk/Sustainability/Environment/fits/Info/Documents1/FIT supplier guidance.pdf which, coincidentally, was published on 26th July.
This, at section 6.8, says:
So OFGEM are telling suppliers that an extension must have an Eligibility Date the same as the Commissioning Date - there is no legal definition in FiTs that supports this.
The upshot is currently that an extension will need to have an EPC dated the same day as the Commissioning Date in order for the customer to get the higher tariff. If it is dated the day after or later then suppliers will put them on the 9p (or now 7.1p) tariff as they will not have shown that they had an EPC 'D' rating on the relevant date.
I am writing to DECC about this aspect of OFGEM's guidance as I cannot see that it is legally supported.
Article 15 of the 2010 FiTs Order (as amended) states quite categorically that extensions must be treated as separate eligible installations. This, to me, means that they should have their Eligibility Date set independently of any existing system.
He had a system installed before EPCs came in and has had an extension installed and commissioned in July this year - just before the 1st August deadline.
He previously did not have an EPC but obviously needed one for the extension.
He had his system installed and commissioned on 26th July and the EPC done on 27th July.
EDF, his FiT supplier, have said that he must go on the 9p rate for the extension as he did not have an EPC 'D' on the required date. They have cited OFGEM guidance on this from here http://www.ofgem.gov.uk/Sustainability/Environment/fits/Info/Documents1/FIT supplier guidance.pdf which, coincidentally, was published on 26th July.
This, at section 6.8, says:
(my emphasis)6.8. The original installation will retain its tariff rate and eligibility period, but the extension will have its own eligibility period and tariff rate. The eligibility date for the extension will be based on its commissioning date only, as the application date is that of the original installation. This means that different eligibility periods may apply to different components of an accredited FIT installation. Payments to the extension will accrue from its eligibility date; therefore the start generation meter reading must be captured on the eligibility date.
So OFGEM are telling suppliers that an extension must have an Eligibility Date the same as the Commissioning Date - there is no legal definition in FiTs that supports this.
The upshot is currently that an extension will need to have an EPC dated the same day as the Commissioning Date in order for the customer to get the higher tariff. If it is dated the day after or later then suppliers will put them on the 9p (or now 7.1p) tariff as they will not have shown that they had an EPC 'D' rating on the relevant date.
I am writing to DECC about this aspect of OFGEM's guidance as I cannot see that it is legally supported.
Article 15 of the 2010 FiTs Order (as amended) states quite categorically that extensions must be treated as separate eligible installations. This, to me, means that they should have their Eligibility Date set independently of any existing system.
Last edited by a moderator: