so this weekend it seems there are just 3 of us available all weekend to do the 2nd phase of a 44kWp install we started last weekend, with one extra panel installer joining us around lunchtime sunday to blitz the panels.
We had originally planned to do it all in 4 days last weekend with 6 staff, but northern powergrid had other ideas and hadn't given permission in time - came though on Wednesday on about day 43 out of their maximum allotted 45 working days, despite us chasing it up and specifically requesting it for the 10th Sept. This weekend half our staff cant' do it.
Inverter is up, cable trays are run, but we've got a total of 4-500m of DC cable in 8 runs (4 strings) to be run, plus AC and testing, and have to lift 88 panels by hand through a roof hatch and along the 40m roof valley, plus do cruciform mounting.
I'm quietly confident that we'll pull it off, but we're going to have to work our backsides off, and be really efficient to do it I think.
so what do you reckon, doable?
place your bets....
We had originally planned to do it all in 4 days last weekend with 6 staff, but northern powergrid had other ideas and hadn't given permission in time - came though on Wednesday on about day 43 out of their maximum allotted 45 working days, despite us chasing it up and specifically requesting it for the 10th Sept. This weekend half our staff cant' do it.
Inverter is up, cable trays are run, but we've got a total of 4-500m of DC cable in 8 runs (4 strings) to be run, plus AC and testing, and have to lift 88 panels by hand through a roof hatch and along the 40m roof valley, plus do cruciform mounting.
I'm quietly confident that we'll pull it off, but we're going to have to work our backsides off, and be really efficient to do it I think.
so what do you reckon, doable?
place your bets....