Where can I take supply from? | on ElectriciansForums

Discuss Where can I take supply from? in the Solar PV Forum | Solar Panels Forum area at ElectriciansForums.net

Joined
Feb 21, 2011
Messages
22
Reaction score
1
Location
Lancaster
Is it possible to take my supply from a 60 amp 3 phase sub board to feed a 38kwp pv system rather than have to go right back to the origin of the supply? I thought you were able to do that but I have recently come across some conflicting reports.
 
Yes in principle it is possible providing amongst other things the PV is on its own circuit from the sub-board. Is there a particular issue you have in mind? The existing sub-main may not be sized for the voltage drop you will be designing for.
 
Yes in principle it is possible providing amongst other things the PV is on its own circuit from the sub-board. Is there a particular issue you have in mind? The existing sub-main may not be sized for the voltage drop you will be designing for.

Hi Bruce, I have run the submain design through my SMA design software and it is showing I am below the volt drop parameter, it was just that a rival contractor quoting for the job had told the customer that you have to take the feed from the origin of supply and I was wondering if there has been any recent guidance from the MCS on the subject.
 
Certainly nothing specific from MCS, they say follow the PV Guide. Page 44 onwards in the PV Guide has the requirements. Must be on its own final circuit. No reason in my opinion that cannot be from a sub-board, provided the normal design criteria are met.

There may be good electrical reasons to go from the origin as the G59 the voltage limits you are working to are stricter than G83, but do the design, including measuring local voltages and supply impedance and you should be able to judge whether using existing wiring is adequate.

There may also be good commercial reasons to go from the origin, as it keeps your work completely separate from existing client installation, which might be helpful if there are faults that need tracking down or if it is claimed the PV is causing problems later. That is a judgement call.
 
Certainly nothing specific from MCS, they say follow the PV Guide. Page 44 onwards in the PV Guide has the requirements. Must be on its own final circuit. No reason in my opinion that cannot be from a sub-board, provided the normal design criteria are met.

There may be good electrical reasons to go from the origin as the G59 the voltage limits you are working to are stricter than G83, but do the design, including measuring local voltages and supply impedance and you should be able to judge whether using existing wiring is adequate.

There may also be good commercial reasons to go from the origin, as it keeps your work completely separate from existing client installation, which might be helpful if there are faults that need tracking down or if it is claimed the PV is causing problems later. That is a judgement call.


Thanks Bruce, pretty much as I was thinking, also just spoke to DNO and they couldn't see any problems as long as usual criteria has been met. I'd like to here from an installer of larger systems though just to get some more feeling of possible issues relating directly to subject.
 
I have installed several 40kw and 50kw installations from sub mains supplies. Some times its impracticable to run cables long distances through buildings. No problems yet with them. I even have my own large scale installation on 3 different buildings all connected to sub mains in the same yard with three different generation meters . Forth meter going in in a couple of weeks to add to system.
 
Hi Bruce, I have run the submain design through my SMA design software and it is showing I am below the volt drop parameter, it was just that a rival contractor quoting for the job had told the customer that you have to take the feed from the origin of supply and I was wondering if there has been any recent guidance from the MCS on the subject.
the other lot are talking a load of rubbish, ask the customer if they'd prefer to pay for your expertise, or their unnecessary cable run.
 

Reply to Where can I take supply from? in the Solar PV Forum | Solar Panels Forum area at ElectriciansForums.net

News and Offers from Sponsors

  • Article
As the holiday season approaches, PCBWay is thrilled to announce their Christmas & New Year Promotions! Whether you’re an engineer or an...
Replies
0
Views
749
  • Article
Bloody Hell! Wishing you a speedy recovery and hope (if) anyone else involved is ok. Ivan
    • Friendly
    • Like
Replies
13
Views
1K
  • Article
Join us at electronica 2024 in Munich! Since 1964, electronica has been the premier event for technology enthusiasts and industry professionals...
    • Like
Replies
0
Views
976

Similar threads

Thank you
Replies
4
Views
403
OK for a simple load. What happens with (say) SMPS LED drivers ? I'd guess : Loads aren't perfectly balanced, especially during startup, so one...
Replies
8
Views
776

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electrical Goods - Electrical Tools - Brand Names Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

YOUR Unread Posts

This website was designed, optimised and is hosted by untold.media Operating under the name Untold Media since 2001.
Back
Top