So yesterday's job was to add a 3ph PV feed into a brand new installation installed by others (the M&E I was doing it for had done the PV side only, the other electrical contractors had decided to skip that circuit and so they'd got me in).
From the first glance it's a nice job, if slightly over-engineered maybe.......
But then I opened the box.....
There's only NINE, brand new circuits, it's an EASY task to dress off, clear the swarf out, not leave combustible paper inside....
???
From the first glance it's a nice job, if slightly over-engineered maybe.......
But then I opened the box.....
There's only NINE, brand new circuits, it's an EASY task to dress off, clear the swarf out, not leave combustible paper inside....
???