How to certify work for inspection before joining Napit or Elecsa?
Afternoon All,
I am qualified to C&G 236 1 and 2 from along time ago! I also meet the criteria for both elecsa and Napit Part P schemes but I am a little confused by the requirement to get an example of my work tested and...
I am currently employed full time with a medium sized contractor in glasgow, scotland and am aiming to go self employed at some point in the next year. However my 2 preferred trade associations want you to be trading 6 or 12 months before theyll sign you up. The question is how does that work...
Hi everyone,
I am planing to join Domestic Installer with NICEIC. And I am thinking to demonstrate my own home for assessment. I will change consumer unit and install a new light circuit and notify to building control via third party. I just wonder this is acceptable?
I know I can ask this...
I’ve been offered a full rewire and consumer unit change, in the guidance note it says all notifyable work should be reported to building control or done by a person who is signed upto a competent person scheme. My aim is to sign upto a scheme eventually, I’ve done a domestic installer course...
Morning lads
I may be mad but I am thinking of starting on my own. Since completing my apprenticeship I have been working mainly on industrial machinery. I have been involved with design through to commissioning stage of installs. Fault finding and plc work are two of my favourite things.
My...
Hi All,
I'm 26 year old, I currently work in hospitality in a managerial role, and I hate it. I've been wanting to get out for ages but unfortunately with having a mortgage and all sorts of bills to pay it`s quite difficult.
I don't have any experience in anything else. I`ve been working bars...
Hi All,
Just wondering what people's thoughts are of joining a Union whilst undergoing a first year Apprenticeship? I'm a mature student (37) and have secured an apprenticeship through JTL. They mentioned about joining a Union, and I was wondering if you think it's worth joining whilst...
Hi any recomendations for products which I can use to join Two 16mm Earth cables. Going in a Fairly inaccesable place so trying to avoid Screw based products. Need to move an bonding cable for Copper pipe as boiler been relocated
Following on from my other thread
IP rated switchcover - https://www.electriciansforums.co.uk/threads/ip-rated-switchcover.173742/
I’ve decide to try and relocate the control panel. After a bit of a faff, managed to get to the other side of the old control panel. So my intention is to extend...
Anyone else had a delay joining Stroma. 5 weeks since my assessment ( passed) and nothing back from Stroma.
On contacting them I get fobbed off with “ there is a backlog “ story.
Whilst Im on the doorstep or retirement, I'm still interested in the world of electrical engineering so I hope you dont mind me joining.
1975 saw me coming out of my time with British Steel Corporation as a full fledge sparky, over the next few years I found myself working on 432Kv and then in...
I was having a debate with my spark today about methods of joining above ground 3 core (E,L,N) 25mm SWA cable. We need to move the consumer unit and with it the meter tails (fused to 80A). This requires an extension of the tails as it is not possible to completely re-run them.
He said that the...
Hello -
I bought a corded hedge trimmer today and started using it. In about 5 minutes I had managed to chop through the cable! Rookie error. Here are the cut cable ends (I am in the UK btw)
So I need to repair the cable. Having googled around, I could solder the wires together, but I don't...
As per title, went to look at kitchen rewire this evening, no probs all straight forward, as I’m about to the leave lady says while you here I keep getting shocked from this wall when I washed it down?
Turns out someone has extended old 4 mm stranded cooker circuit with 2.5 and put a double...
Hi, neighbour has asked me if I would move his cooker control switch for him. Since new position of it is further away,this would require joining existing cable via JB or, as is preferable, running a new cable. Running a new cable is a fairly big job,so do the regs allow a JB to be used in this...
Hello I have been working with electrical sector since 1980 , timeserved electrical fitter, electrical machine tool fitter, test and development engineer for a large uk shower manufacturer, then an instructional officer in a prison ( a really interesting job). I have struggled to stay employed...
On site today and heard the carpenter tell the site manager that all the sockets and switches on the joining wall (flat opposite side) will need to have fire prevention boxes built aroud them.
The site manager is having trimber supports added for the sockets and told him there is fire...
Hi all,
I'm attempting a repair on a comfort zone underfloor heating mat.
The customer lifted a floor tile and in doing so cut through the cable. Fortunately there is enough slack to complete a join but I have one shot left at this having already tried with butt connectors and heat shrink...
hi,
Looking for an IDC punch down connector block similar to a 1x9 telephone bridging module in an enclosure that can be used to join up the cat5 cables for a door entry system.
Any ideas if such a thing is available?
Alternatively how do people connect up the multitude of cat5 cores neatly...