Hi
Im Looking for some advice on compliance as its a bit of a gray area
Kitchen currently has 13a FCU fed from ring main and 2.5mm lsf to single gang skt for washing machine.
Want to change this to
20a DP switch and spur off the single gang socket for washing machine and fit second single gang skt for dishwasher.
Reason for not fitting new FCU and separate supply is its a brand new house and would have to destroy tiles.
I realise the current capacity of the 2.5 is round 20a but the washing machine and dishwasher are no where near pulling that even with both heaters on at same time and taking diversity in to account would imagine it is unlikely to ever have both machines on the heating phase at the same time.
Would this be acceptable ?
Im Looking for some advice on compliance as its a bit of a gray area
Kitchen currently has 13a FCU fed from ring main and 2.5mm lsf to single gang skt for washing machine.
Want to change this to
20a DP switch and spur off the single gang socket for washing machine and fit second single gang skt for dishwasher.
Reason for not fitting new FCU and separate supply is its a brand new house and would have to destroy tiles.
I realise the current capacity of the 2.5 is round 20a but the washing machine and dishwasher are no where near pulling that even with both heaters on at same time and taking diversity in to account would imagine it is unlikely to ever have both machines on the heating phase at the same time.
Would this be acceptable ?