dave992
-
hi,
Testing a job at the moment and a couple of DB have all there CPC connected in the trunking instead of the DB. There is a earh bar within the metal trunking but due to the trunking full of cables, unabale to gain access to the CPC. Due poor access to the CPC ive made a report on that but is the earh bar in the trunking ok?
Thanks dave
Testing a job at the moment and a couple of DB have all there CPC connected in the trunking instead of the DB. There is a earh bar within the metal trunking but due to the trunking full of cables, unabale to gain access to the CPC. Due poor access to the CPC ive made a report on that but is the earh bar in the trunking ok?