M

MTI

Ok guys looking for some advice. Will be contacting my scheme provider and LABC tomorrow.

basically builder starts wiring an extension and then calls me in to finish it and sign off. I told them i cant do that and it will need putting right as i cant even see their first fix due to plastering. Expressed this to customer too.

customer asks you to do work in other areas to be renovated to include putting right existing (not builders work) and alter/upgrade things to suit building works. You agree to work direct for customer on agreed day rate plus materials.

You do all you can for customer and help out builders by fitting in with their work to suit as you go along. Bits get done here and there as needed. Things are incomplete here and there and certain things need putting right as agreed with customer prior to works starting

Builder takes tons of cash from customer and requests more and more in a short period of time equating to more than agreed price. Customer gets upset although you have worked directly for customer and are not involved because builder quoted a ballpark in his amount for electrical and you told customer that is nothing to do with you and you agreed a day rate and estimate timescale. I did a ton of work like i was on price!

Customer makes part payment for a couple of days work and materials delivered and is happy. You then go away for a few days to come back and find customer is v upset and cant afford to continue. On top of this, builder has tried to do more work to get further money, not be kicked off job and even has installed more circuits in many places, altered yours and caused chaos in a nutshell!

Given that id first and second fixed an area hoping to come and test and energize on my return to find out its been altered massively is not my fault. Another example is one area/new extension required a sub CU fed from main board so id installed some circuits before i went away and did a bit of 2nd fix here and there and mounted new said board. Builder alters and adds cables in non prescribed zones!!!! to suit further work whilst your away so they can board areas.

At the end of all this, customer will not pay up and i cannot complete the works i did, remove and put right the wrong bits that builders did nor test and cert. I cant even say if alterations are energized now where id been working and not got to complete as along with others were told to pack up and leave on what was just supposed to be another normal day at work!

its a real royal mess! please advise guys and please do not shoot me down. this is out of my control! and i said id never work for builders and i didnt - i worked for customer who shot me instead! out of pocket and out of mind!
 
hit and a miss with the builders, i`m deep in s*it now too, got half of 4 bedroom rewire payment after first fix done,
to be paid other half when completing the job. builder firm went bust on 90% completed job, after taking more than quoted amount from the customer. including my and plasterers 2nd fix money...

thats pants mate - sorry to hear it - been there so thats why i dont work for builders but todays customers can be just as bad pulling a fast one!

anyway, thanks for keeping up the guidance guys - it does help you put mind at rest. Im going to sod the client and just inform my scheme and labc without warning and not get involved more than needed. I dont need to let people stew in the meantime. let it all crash at once!
 
In my part of the world. Sparks spark. Builders put blocks up and rest on a shovel .
We do not have part p so I can only look on with joy that we don't have that mess to deal with. If a building warrant is on a build the certification gets issued on payment unless I know them well.select want you to issue them before hand. But as previos post they ain't ginna starve eh?i used to do work or a guy like this and to be honest the animosity he caused between customers and the trades was unreal.It was a relief after one too many shady moves he got told gtf.are they not trying to bring in 3rd party certification in the new part p? There will be no sparks left then ...the builder will do it all
 

Reply to Customer doesnt want us to complete! in the UK Electrical Forum area at ElectriciansForums.net

News and Offers from Sponsors

  • Article
Join us at electronica 2024 in Munich! Since 1964, electronica has been the premier event for technology enthusiasts and industry professionals...
    • Like
Replies
0
Views
289
  • Sticky
  • Article
Good to know thanks, one can never have enough places to source parts from!
Replies
4
Views
792
  • Article
OFFICIAL SPONSORS These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then...
Replies
0
Views
822

Similar threads

  • Question
In the mind of someone lying there wide awake at 3AM, just about anything.
    • Like
2
Replies
25
Views
3K
  • Question
After fitting out the first room of downlights.... i expect him to get a bit speedier at fitting them There is so many unknowns to price at this...
2
Replies
25
Views
2K

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electrical Goods - Electrical Tools - Brand Names Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

YOUR Unread Posts

This website was designed, optimised and is hosted by untold.media Operating under the name Untold Media since 2001.
Back
Top