infinity
-
HI, Ive got an install next week, i was wondering how are you all getting on with commissioning the array if its gone 4pm and the suns disappeared?
I wont really have time to go back in the day as they are in different areas. Any advice much appreciated.
Also do you all clip direct your dc cables to the joists all the way to the inverter or put in containment? All very new to me and i really want to get it all right.
I wont really have time to go back in the day as they are in different areas. Any advice much appreciated.
Also do you all clip direct your dc cables to the joists all the way to the inverter or put in containment? All very new to me and i really want to get it all right.