DECC launch FIT review | Page 21 | on ElectriciansForums

Discuss DECC launch FIT review in the Green Lounge (Access Only) area at ElectriciansForums.net

Looks like EPC of D status stays but must be before date of commissioning.

Apologies if this is a stupid question - so the D rating must be achieved without including the solar? The vast majority of our work doesn't qualify because if oil/lpg installations if that's the case.
 
Is there any indication that costs are going to drop? We're really sitting on the fence with this. We were going to do a bit more property development but our capital is tied up in a house we're letting to flood victims for the next 6 - 8 months so I could do with keeping solar going for a bit longer but can't really make the figures stack up.
 
I'm not sure how much more panel prices can drop what with the Minimum Import Price so that only really leaves Inverters and mounting.

I'm lucky as I live in the South East so can easily generate 1000kWh per kW installed so the numbers stack up better down this way whereas in Edinburgh for instance it's 852kWh per kW installed.

I'd imagine there'll be a lot less competition as well when the ex double glazing lot bugger off.

Storage is an option but not quite ready yet.
 
Return on a 4kWp at 1000 kWh/kWp

gen tariff 4000 x 4.39p = ÂŁ175.60
export 4000 x 50% x 4.85p = ÂŁ97.00
offset 2000 x 13p = ÂŁ260.00

total = ÂŁ532.60

to get:
7 year break even = install cost ÂŁ3728.20
8 year break even = install cost ÂŁ4260.80
9 year break even = install cost ÂŁ4793.40

compared to the pre-15th January rate of 12.03p

gen tariff 4000 x 12.03p = ÂŁ481.20
export 4000 x 50% x 4.85p = ÂŁ97.00
offset 2000 x 13p = ÂŁ260.00

total = ÂŁ838.20

to get:
7 year break even = install cost ÂŁ5867.40
8 year break even = install cost ÂŁ6705.60
9 year break even = install cost ÂŁ7543.80

So looking at the 8 year break-even you have a difference of 6705 - 4260 = ÂŁ2445. I can't imagine prices can drop that much.

Over the full 20 year life it is a reduction for the householder of (838 x 20) - (532 x 20) = 16760 - 10640 = ÂŁ6120
 
I'm staying positive and am confident we can install 4kW systems circa ÂŁ5500-ÂŁ6000.

What I think will happen though is there will be a lot more >4kW+ systems coming under the 10kw banding 'space permitting'.

That would greatly improve the ROI as our installation charge isn't going to double for say an 8kW system over a 4kW.

The Old Tariff bands did warp the market slightly, what we need now is a better way of asking for DNO permission for the slightly bigger systems or even better, the removal of the 16amps per phase limit so we can get on with the installations quicker especially considering the new caps (which I must admit, I'm not quite sure I fully understand yet).

Either way this is going to a testing time.
 
Apologies if this is a stupid question - so the D rating must be achieved without including the solar? The vast majority of our work doesn't qualify because if oil/lpg installations if that's the case.

What if the date of the PV commissioning and the EPC are the same? I do our EPCs personally when the panels are on the roof and include the PV to give the score a "boost". Usually it's not necessary to get the D but occasionally it is.

It seems silly to me to do the EPC in advance as it will be inaccurate within a couple of weeks when the PV is added. It makes much more sense to do it either at the same time or after the PV has been fitted.
 
on the plus side, there could be some add on work to get the D rating prior to the PV going in, and often the add on work is better payback time than the PV will be, so that could improve overall payback.

Some of it can be pretty simple, like replace heating controller, add thermostats, add insulation jacket to water cylinder, top up loft insulation, add chimney balloon etc.

ALso SRE - you may be aware of this or may not, but IME most supposedly solid stone walls actually have a small cavity if you drill through them, sometimes rubble filled, sometimes not, but EPC assessors usually treat them as if solid. Makes quite a difference if the EPC assessor puts into the software as having a small cavity rather than being solid wall. One of the main reasons that the real world performance of external wall insulation on solid wall properties was nothing like as good as SAP predicted.
 
Interesting point about the cavity Gavin. Most of ours need boiler changes so it's a major change but the cavity situation might make a difference.
 

Reply to DECC launch FIT review in the Green Lounge (Access Only) area at ElectriciansForums.net

News and Offers from Sponsors

  • Article
Join us at electronica 2024 in Munich! Since 1964, electronica has been the premier event for technology enthusiasts and industry professionals...
    • Like
Replies
0
Views
285
  • Sticky
  • Article
Good to know thanks, one can never have enough places to source parts from!
Replies
4
Views
789
  • Article
OFFICIAL SPONSORS These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then...
Replies
0
Views
810

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electrical Goods - Electrical Tools - Brand Names Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

YOUR Unread Posts

This website was designed, optimised and is hosted by untold.media Operating under the name Untold Media since 2001.
Back
Top