Hi all,
Hope you are all well and all is good!
I am installing a sub board being fed by a 80A SP+N Metal Switch Fuse at source, this is feeding a 25mm 3 core SWA at a length of about 2 meters to the main DB (both boards are metal). I am being challenged in saying that I have to add an earth fly lead at both ends, preferably the same size as the CPC e.g. 25mm, as the glands will be fine for continuity of CPC into the armour.
Am I being super safe or just a moron, whats the right answer?
Thanks all.
Hope you are all well and all is good!
I am installing a sub board being fed by a 80A SP+N Metal Switch Fuse at source, this is feeding a 25mm 3 core SWA at a length of about 2 meters to the main DB (both boards are metal). I am being challenged in saying that I have to add an earth fly lead at both ends, preferably the same size as the CPC e.g. 25mm, as the glands will be fine for continuity of CPC into the armour.