How would you record the install? MWC for the main DB to garage DB ( assuming using MCB that is there already and has 6mm cable just re-routing) and EIC for garage DB

House CU to garage is “new circuit” and garage DB is a “new CU”, so both require an EIC to be issued and LBC notified.
 