Hi Folks, First time post here.....
I'm about to start upgrading my kitchen - and I've got a few bits of wiring to sort. No big issue, but the main thing that needs doing is the backboard for the consumer unit needs changing. Reason being - there used to be an electric storage heating system fitted, with its own meter and CU. This has been removed, however the board is rotten and the old tails are still wired into the fusebox (but checked and and not live!) They are capped/taped up and just sitting behind the hole where the old heating CU was.
The old fusebox at the bottom - I assume to have ONLY the cutout fuse in it, and not an isolator switch?
I Guess the problem here is the tails up to the consumer unit are constant live, and without removing the CU, I'll not be able to change that back board.
Option 1 : Cut the seal on the fuse box and(I assume) cutout fuse, Fit an DP 100a isolator switch, and then go safely about the jobs I need to do.
Option 2 : Contact my energy supplier who will fit an isolator switch for just ÂŁ60 -however its a 4 week wait, and that will essentially hold my kitchen up for those 4 weeks.
I'm open to any suggestions or advice (other than working it live.....)
I'm about to start upgrading my kitchen - and I've got a few bits of wiring to sort. No big issue, but the main thing that needs doing is the backboard for the consumer unit needs changing. Reason being - there used to be an electric storage heating system fitted, with its own meter and CU. This has been removed, however the board is rotten and the old tails are still wired into the fusebox (but checked and and not live!) They are capped/taped up and just sitting behind the hole where the old heating CU was.
The old fusebox at the bottom - I assume to have ONLY the cutout fuse in it, and not an isolator switch?
I Guess the problem here is the tails up to the consumer unit are constant live, and without removing the CU, I'll not be able to change that back board.
Option 1 : Cut the seal on the fuse box and(I assume) cutout fuse, Fit an DP 100a isolator switch, and then go safely about the jobs I need to do.
Option 2 : Contact my energy supplier who will fit an isolator switch for just ÂŁ60 -however its a 4 week wait, and that will essentially hold my kitchen up for those 4 weeks.
I'm open to any suggestions or advice (other than working it live.....)